# How do you build and manage a project schedule?

We host this **Program Sense** question for Engineering Manager, Technical Program Manager, and Software Engineer roles. It is associated with Crusoe, Salesforce, Microsoft, and Dropbox. The page records **4 interviews** and **2 shared interview experiences**. Detailed company statistics are available through [Upgrade](https://www.aced.io/upgrade?src=questions).

## Interview experiences

- [Crusoe · a month ago](https://www.aced.io/experiences/crusoe-senior-engineering-manager-interview-086474) — Engineering Manager · Senior / L5. “The interview went well overall, but I wish we had spent more time discussing technical topics in depth rather than just covering them at a high level.”
- [Salesforce · 6 months ago](https://www.aced.io/experiences/salesforce-senior-technical-program-manager-interview-291a42) — Technical Program Manager · Senior / L5. “The overall interview was over in a week. I think they were looking to quickly to finish the round. It's for Missionforce. The feedback came in positive but for some reasons unknown and not shared they didn't went ahead with me.”

## Community answers

### Danyal R.

[Danyal R.](https://www.aced.io/users/53cd8c66-3c0c-4022-b455-0b7afbf0366a) · Member · [1,219 karma](https://www.aced.io/karma) · August 22, 2023

The proposed process is:

#### Do your homework

- Align goals with the team and stakeholders.
- Include externally committed deadlines in planning.
- Set up effective communication channels for the right audiences—for example, scrum with engineering and product reviews with leadership.
- Publish a one-page summary of project goals, execution plan, and resources to drive accountability, alignment, and collaborative decision-making; iterate based on feedback.

#### Build a case after alignment

- Estimate resource requirements with cross-functional partners.
- Align dependencies with engineering, design, research, QA, legal, and privacy stakeholders.
- Map out the MVP.
- Eliminate potential risks such as privacy and legal risks.

#### Validate the case

- Align with engineering counterparts on milestones, such as phase 1 and phase 2.
- Set up dogfood channels to collect feedback after phases are complete.
- Include time to iterate and fix bugs.

#### Execute

- Use a collaborative scheduling tool such as Jira or MS Planning to write user stories and assign engineering work.
- Create standing check-ins, such as daily scrum meetings.
- Report progress through monthly product reviews and weekly reports.
- Maintain a channel for post-launch ideas, such as a backlog.
- Communicate often.

### Saket S.

[Saket S.](https://www.aced.io/users/96f8f5b7-dbb3-451e-beeb-7be269928425) · [1,036 karma](https://www.aced.io/karma) · March 11, 2022

A project schedule is a **living document** built from inputs across product, engineering, finance, sales, marketing, legal, and other teams. The Project/Program Manager owns it, but it reflects the whole team’s progress. Inputs include the project charter, stakeholder list, project scope, work breakdown structure (WBS), freeze calendar, and vendor statements of work (SOWs).

Schedule-development steps:

1. Copy the milestone-level plan from the project charter into Microsoft Project.
2. Meet with the team to establish high-level or summary tasks for each milestone, such as setting up a test environment.
3. Ask cross-functional team members to break summary tasks into detailed tasks. For example, setting up a test environment can include building virtual machines, installing the application, and installing the database.
4. Sequence tasks based on team feedback and assign predecessors and successors.
5. Assign resources.
6. Schedule tasks using resource calendars and freeze calendars, with start and end dates.
7. Identify and color-code critical-path activities.
8. Use a separate color code for cross-team dependencies.
9. Review the schedule with the business, obtain sign-off on the overall timeline, and save it as the baseline.

For schedule management, review and update the schedule regularly as progress and details change. If technical or external issues cause missed deadlines, re-plan tasks and submit a change request to re-baseline the schedule. For Agile projects, prepare the schedule from sprint- and release-planning outcomes.

### Priya P.

[Priya P.](https://www.aced.io/users/58e1807d-6fd1-440d-b886-e5e14684283e) · [80 karma](https://www.aced.io/karma) · February 3, 2022

The suggested starting sequence is to define project goals, identify responsible parties, understand the project, create a timeline, identify the appropriate skills, assign tasks, follow up on status daily, and track project performance.

## Related questions

- [How do you sunset a project?](https://www.aced.io/questions/1028/how-to-sunset-a-project)
- [How do you manage projects under pressure?](https://www.aced.io/questions/3406/manage-projects-under-pressure)
- [How have you managed risk in a project?](https://www.aced.io/questions/931/managing-risk-in-project)

## Related courses

### [Engineering Management Interview Prep](https://www.aced.io/courses/engineering-management)

We prepare candidates for engineering manager roles at Meta, Google, Amazon, Microsoft, Stripe, and other top companies through mock interviews, frameworks, and senior-candidate advice covering system design, people management, project retrospectives, behavioral interviews, and more.

### [System Design Interviews](https://www.aced.io/courses/system-design-interviews)

We cover current system-design questions across product, infrastructure, and AI, with in-depth video examples, written breakdowns, reference patterns, and mock-interview videos from senior engineers and managers.

---

[Read this page’s summary](https://www.aced.io/agents/api/public/v1/page-tldr?url=https%3A%2F%2Fwww.aced.io%2Fquestions%2F1027%2Fhow-to-build-manage-project-schedule&trace=t_679ff9ab98f3)

## Ask a follow-up about this page

Need a more specific answer? Ask the exact question you have. It returns a fresh, cited answer from Aced (formerly Exponent)’s knowledge base. No account or API key required.

Open this URL with your own question, URL-encoded. Include your question in q. All research inputs are optional; no account or setup.

`GET https://www.aced.io/agents/agent/faq?q={question}&trace=t_679ff9ab98f3`

[Tool guide and examples](https://www.aced.io/agents/agent-access) · [OpenAPI](https://www.aced.io/agents/api/public/v1/openapi.json) · [Page TLDR form](https://www.aced.io/agents/agent-tools/page-tldr?url=https%3A%2F%2Fwww.aced.io%2Fquestions%2F1027%2Fhow-to-build-manage-project-schedule). Opening a form does not execute a tool.